One to three days, start to finish
Installation is the part of a kitchen that decides whether the drawings were worth anything. A run can be perfectly made and still look wrong if the boxes are not level to each other, if the doors are not set to the same gap, or if the panel against the wall was cut on site with a jigsaw. So we do it ourselves, with the people who made the cabinetry, and we plan the day before the truck is loaded.
The sequence is always the same. The old kitchen comes out and leaves in the same trip. Base cabinets go in first, set on adjustable levellers and checked with a long level across the whole run, not cabinet by cabinet. Once the bases are true they are screwed to each other and to the wall, and the uppers are hung off a ledger so nothing is held by hand while it is fixed. Panels, fillers and toe kicks are scribed to the wall and the floor, which is the step that separates fitted cabinetry from delivered furniture. Doors and drawers go on last, then every hinge is adjusted in three directions until the gaps read as one line across the room.
In most kitchens the countertop is templated after the boxes are standing and installed a few days later, so there are two visits: the fit, then the stone and the sink. Plumbing and electrical connections are done by licensed trades, and we book them for the day the stone lands rather than the day the boxes arrive. Nothing about that order is negotiable, because the alternative is a sink cut from a drawing.
What happens on installation day
- Protection first: floor covering, door frames wrapped, a path to the truck.
- The old cabinetry is removed and taken away, not stacked in the garage.
- Bases levelled across the full run, then locked together and fixed to the wall.
- Uppers hung, tall units plumbed, appliance openings verified against the real appliances.
- Panels, fillers, toe kicks and crown scribed and fitted.
- Doors, drawers and hardware set, then the room is cleaned and walked with you.
What actually slows a day down
Three things, and none of them are the cabinetry. An appliance that has not arrived, so the opening cannot be verified. A floor that is being replaced after the kitchen instead of before it, which forces the toe kicks to be refitted. And access: a booked elevator that is no longer booked, or a stairwell that turns at ninety degrees with no landing. We ask about all three at the measure, which is why the visit takes forty minutes rather than ten.